As reported on November 18, 2026, MARA Holdings’ planned acquisition of Long Ridge Energy & Power illustrated a change in how the miner uses its bitcoin reserves. MARA first pledged BTC to raise dollars for the transaction, then sold BTC to repay the acquisition loans before the deal closed. In results released on November 9, the company disclosed that it had sold approximately 40,581 BTC during 2026, raising about $3 billion.

From accumulating BTC to funding obligations

MARA adopted a policy in July 2024 of retaining all the bitcoin it mined while also buying BTC on the open market. Its holdings reached 44,893 BTC by year-end; in the fourth quarter alone, it bought 15,574 BTC with convertible-debt proceeds. In 2025, the company began permitting sales of newly mined bitcoin. In 2026, it extended sales to BTC already on its balance sheet.

Between March 4 and 25, 2026, MARA sold 15,133 BTC for approximately $1.1 billion. It then spent about $913 million to repurchase two series of zero-coupon convertible notes with roughly $1 billion in principal. The repurchase reduced outstanding principal and the potential dilution if the notes were later converted into shares.

During the first nine months of 2026, MARA mined 6,916 BTC and sold approximately 26,984 BTC. It held 34,012 BTC at September 30, down about 37% from year-end 2025, but only 14,752 BTC was freely available; the rest was pledged or lent. Total holdings and immediately usable holdings had become different measures of its financing capacity.

How the Long Ridge financing worked

MARA announced in late April that it planned to acquire Long Ridge from FTAI Infrastructure at an enterprise value of approximately $1.5 billion, including up to about $900 million of debt it proposed to assume. On August 4, it arranged $750 million in BTC-backed loans: $450 million from Coinbase Credit, including $150 million to refinance an existing loan, and $300 million from Two Prime Lending. The loans provided $600 million in new funding against an initial pledge of 18,750 BTC.

MARA said bitcoin was worth about $64,000 when it borrowed. Pledging BTC gave the company dollar funding without immediately selling the coins or issuing shares, but exposed it to interest costs and collateral calls if BTC fell. The Two Prime loan carried a 7.65% annual interest rate; the Coinbase loan had a floating rate. Under the loan terms, failure to address a collateral shortfall could allow lenders to dispose of pledged BTC.

After the third quarter ended, MARA sold 13,597 BTC at an average price of about $81,039, raising roughly $1.1 billion. It used $750 million to repay both loans in full and recovered the 17,477 BTC still pledged against them. Management estimated that borrowing first and selling later produced a net benefit of about $170 million. That outcome depended on the price path: a decline before closing could instead have brought collateral pressure alongside a lower sale price.

The US Federal Energy Regulatory Commission approved the acquisition on November 4. When MARA reported results on November 9, it still expected to close in the following weeks. Repayment of MARA’s BTC-backed acquisition loans did not eliminate Long Ridge’s existing debt, which remained part of the proposed transaction.

The cash-flow question behind the deal

Long Ridge owns an operating natural-gas power plant in Hannibal, Ohio, with 485 megawatts of capacity currently authorized for sale. MARA expected it to reach 505 megawatts of nameplate capacity in the first half of 2027. According to the company, long-term contracts already covered about 70% of the plant’s output. The transaction also included more than 1,600 contiguous acres; MARA had an approximately 200-megawatt facility nearby.

An operating plant could provide electricity-sale revenue while the company develops data-center capacity. But contracted power is not automatically available to new computing customers, and the scale and timing of any data-center project still depend on subsequent arrangements, construction and financing. MARA also had a proposed Texas development with up to 2 gigawatts of potential power supply, subject to approvals including grid connection. It hoped to sign two data-center leases by the end of 2026 but said signing could slip into 2027.

MARA’s controlled subsidiary Exaion had signed a four-year, $79 million GPU-compute services contract with its first US customer. That contracted service differs from leasing data-center space and infrastructure. More than $3 billion in potential opportunities disclosed by MARA had yet to become binding orders individually.

The distinction between accounting gains and cash is material here. MARA mined 2,247 BTC in the third quarter, up about 5% year over year, while revenue fell 35% to approximately $164 million. Net income of about $632 million included roughly $885 million in digital-asset fair-value gains. Those gains could raise reported profit; acquisitions, interest and construction require cash.

On November 9, MARA’s board also authorized up to $500 million in share repurchases, without committing to a purchase amount or timetable. In its shareholder letter, the company listed AI-infrastructure investment, possible convertible-note put exercises beginning in 2027, and potential buybacks among future uses for funds raised by selling BTC. The unresolved question is how much cash the power plant and prospective data-center projects can generate—and how much bitcoin MARA may need to sell before that cash arrives.